130758 | This line extension agreement is for a main extension consisting of a two (2) inch PE Class 200 main to serve four buildings on developer’s property for both domestic and irrigation service. Costs for the project shall be borne by the developer and an additional eight (8) connections will be purchased in the amount of $12,880. All work done by developer shall be built to the water company’s construction standards and shall be subject to passing inspection by the water company’s engineer prior to acceptance. Developer shall convey to South Bainbridge Water Systems the main and appurtenances. The company serves approximately 1,200 customers in Kitsap County. |
091882 | Amendment to an agreement to provide fire flow that became effective January 4, 2010, by operation of law. The amendment changes the form of security to allow an assignment of funds in lieu of a performance bond, and has no financial impact on contract costs. South Bainbridge serves about 1,250 customers, on the south end of Bainbridge Island in Kitsap County. |
091883 | Agreement to serve up to eleven (11) additional connections with eleven (11) equivalent residential units (ERU). Cost is $2,424.32, Water System Facility Charge, per ERU and $750 attorney fee. The agreement also has a provision for ERU buyback by the water company should the developer not use all eleven (11) ERUs. Service connection charges shall apply under the company’s tariff at the time connection is actually made to the water system. Monthly ready-to-serve charges for this service are based on the company’s tariff rate. |
091696 | Main extension agreement for water service to a single lot with one equivalent residential unit. Costs for the line extension shall be borne by the developer. Additionally, a late-comer provision for a period of eight years is agreed to for two potential future connections. |
080264 | Developer-financed Line Extension Contract for two-inch (2”) line on customer property, with assorted valves and other appurtenances. Contract is to serve four (4) mixed use buildings for the parcel developed by Rich Pass, LLC. Contract includes an acknowledgment that customer requires fire flow through a six-inch (6”) ductile iron main off of the main extension. Customer will pay Twenty Five Cents ($0.25) per one hundred square feet of building space per month; customer building size is forty-four thousand ten (44,010) square feet resulting in a charge of One Hundred Ten and .02/100 dollars ($110.02) per month for this service. Contract also includes installation of backflow prevention devises to ensure water from other sources does not enter South Bainbridge’s water system. The domestic connections to serve mixed use buildings and irrigation will equate to twenty (20) connections. |
072069 | Developer-financed Line Extension Contract to serve one parcel known as Rich Pass, LLC. Customer cost will be approximately $30,000.00 Contract is for 635-feet of eight-inch (8”) ductile iron pipe, including at least two fire hydrants, with assorted valves and other appurtenances. Contract also includes an acknowledgment that customer requires fire flow and will pay Twenty Five Cents ($0.25) per one hundred square feet of building space per month; customer building size is five thousand four hundred thirty-three (5,433) square resulting in a charge of Thirteen and 58/100 dollars ($13.58) per month for this service. Contract also includes installation of backflow prevention devises to ensure water from other sources does not enter South Bainbridge’s water system. The domestic connection to serve a commercial restaurant is a one and one-half inch (1-1/2 inch) meter. |
071675 | Developer-financed Line Extension Contract to serve two parcels. Customer cost will be approximately $22,000. Contract is for 125 feet of eight-inch (8”) ductile iron pipe, including at least one fire hydrant, with assorted valves and other appurtenances. Contract also includes installation of backflow prevention devises to ensure water from other sources does not enter South Bainbridge’s water system. |
071584 | Developer-financed Line Extension Contract to serve one lot. Customer cost will be approximately $56,000. Contract is for 700-feet of eight-inch ductile iron pipe with assorted valves and other appurtenances. Contract also includes an eight-year late comer's agreement that could impact three additional lots. Each latecomer will be assessed a latecomer’s fee equal to one-fourth (1/4) of the final cost of the line extension, plus interest from the date the original customer has paid for main extension at the rate of eight percent simple interest to provide a shared payback of cost. |
070298 | Developer-financed Line Extension Contract to serve four lots. Customer cost per lot will be shared equally. Contract is for 680-feet of six-inch ductile iron pipe to include at least one fire hydrant and assorted valves and other appurtenances. Contract also includes an eight-year late comer's agreement with an equal share payback of cost. |
061776 | Developer-financed Line Extension Contract to serve two lots. Customer cost per lot will be about $12,500 per lot. Contract is for 300-feet of six-inch ductile iron pipe to include at least one fire hydrant. Contract also includes an eight-year late-comer's agreement with a pro-rata share of cost. |
061635 | Developer-financed Line Extension Contract to serve eight lots, per lot at $12,165. Contract is for 845-feet of eight-inch ductile iron pipe to include at least two fire hydrants and assorted valves and other appurtenances. Contract also includes an eight-year late-comer's agreement with an equal share payback of cost. |
061504 | Developer-financed Line Extension Contract to serve two lots. Customer cost per lot will be $7,500. Contract is for 280 feet of six inch ductile iron pipe to include at least one fire hydrant. Contract also includes an eight year late comer's agreement with a pro-rata share of cost. |
060668 | Company has filed a developer-financed line extension contract to serve three parties. Line extension will be about 820 lineal feet. The contract also contains an eight-year latecomer agreement for a pro-rate share reimbursement.
South Bainbridge Island Water Company is located on the South end of Bainbridge Island and serves about 1,200 customers. |
060112 | Water System Extension Agreement between South Bainbridge Water Systems, Inc., and Cascade Evergreen for a 250-foot, six-inch line extension to serve three lots along NE South Beach Drive. Construction cost estimate is unknown. Line extension to be funded by developer and contributed to South Bainbridge Water Systems, Inc. |
060094 | Line Extension Contract between South Bainbridge Water Systems, Inc., and Harry Abernathy for a 450-foot line extension to serve one lot at 4050 Crystal Springs Drive. Construction cost estimate is unknown. Line extension to be funded by developer and contributed to South Bainbridge Water Systems, Inc. |
051231 | Contract for water service not contained in Company's tariff. Contract for service is temporary pending permanent engineering and construction consideration for service to Kitsap County Consolidated Housing Authority located at 4500 Pheasant Beach Drive, Bainbridge Island, Washington. Temporary service will be considered equivalent to four residential units. |
050875 | Developer-financed line extension to serve two lots on White Point Drive. Customer Lange to fund line extension with eight-year late-comer agreement for one additional lot. |
042139 | First Amendment to a developer-financed line-extension contract for 1,071 feet of six-inch piping and booster station to serve three lots. Includes eight-year latecomer provision and the line extension will to be turned over to the Company when completed. |
041936 | Addendum to a developer-financed line-extension contract to serve three lots. Line extension of 600 feet of eight-inch piping to serve residential lots of C. White, W. Carter, and S. Carter. Line extension to be turned over to South Bainbridge Water by Bill of Sale, when completed. |
041902 | Developer-financed line-extension contract to serve two lots. Line extension of 288 feet of six-inch piping to serve Sine Metu Holdings, LLC. Provides an eight-year late-comer agreement for service to three additional lots at equal costs, plus interest. |
040355 | Developer financed line extension to serve four lots on Point White Drive and line extension of 390 feet, 8-inch ductile iron pipe. Agreement is for three lots with 4th lot subject to 25 percent late-comer agreement for 8-year period. |
030659 | Contract to provide water service and fireflow to Lynwood Commons 4765 (two retail, ten-unit apartment complex). |
030660 | Contract to provide water service and fireflow to Lynwood Commons 4779 (one retail, ten-unit apartment complex). |
030635 | Line extension agreement between South Bainbridge Water Systems, Inc., and Sunny Hill Properties, LLC, for 1700 feet to serve Sunny Hill Short Plat. |
030144 | Contract of South Bainbridge Water System, Inc., to acquire the water system operated by the West Port Blakely Water Association. |
021571 | Service connection contract requesting waiver of WAC 480-110-445 (1) and (5), to locate connection at existing main. Customer to install own service line across private property. |
021298 | Water system agreement between South Bainbridge Water System, Inc., and Lynwood Commons, LLC. |
020995 | Line extension agreement between South Bainbridge Water Systems, Inc., Bonita Decker, and Peter McCormack. |
020695 | Line Extension Agreement between South Bainbridge Water Systems, Inc., and South Beach Condominiums, LLC. |
011381 | Extension Agreement - Ecklund - Request to Waive WAC 480-110-445(1) and (5) - (Service connection charge and service connection length). |
001568 | Less than statutory notice request to approve water main replacement contract between South Bainbridge Water System, Inc., and Frank R. Kitchell. |